Loomis Courts Redevelopment Timeline
| Phase/Milestone | Period | Notes |
| ABLA Leadership/Stakeholder Engagement | Feb 2026 – ongoing | Biweekly ABLA and monthly Loomis meetings |
| Loomis Resident Engagement | Spring 2026 – ongoing | Resident engagement and meetings around design and construction processes; resident training, hiring and business opportunities; resident services and other project updates. Identify resident services priorities and partners. |
| Site & Building Investigations | Spring/Summer 2026 | Environmental, structural, building needs survey |
| Redevelopment Planning | Summer/Fall 2026 | Resident-centered process to create the concept plan for redevelopment |
| Design Process | Winter 2026 – Summer 2027 | Design team led by Canopy will complete construction drawings needed for building permit and construction. Residents engaged and updated throughout design process. |
| Selection of General Contractor | Winter 2026 | Request for Proposals (RFP) for General Contractor (GC) issued, requiring GC’s commitment and plan for Section 3 business participation and resident hiring. |
| Plan for Section 3 Participation and Community Hiring | Spring/Summer 2027 | Work with selected General Contractor prior to construction starting on details of the Section 3 participation and resident hiring plan including: scopes, positions, and experience needed for project; matching process for interested residents and new positions, and current and potential new Section 3 businesses for project scopes; Section 3 certification process; supports for businesses and residents during pre-construction and construction. |
| Financing Application and Approvals | Summer/Fall 2027 | Tax credits, loans, CHA financing, HUD |
| Financial Closing | Winter 2027 | All approvals for financial closing complete, and financing complete |
| Construction | Winter 2028 – Summer 2029 | Renovate both buildings and construct new amenity center |
| Re-Occupancy / Lease-Up | Summer 2029 | Coordination with Loomis residents will start prior to construction completion to facilitate a smooth re-occupancy process. |
| Ongoing Operations | Summer 2029 – beyond | Ongoing property management and resident services and support |
upcoming meeting:
previous Meetings:

October 24, 2026
10:00 am
Jane Addams Family Resource Center
1254 S. Loomis Street, Chicago, IL 60608

July 11, 2026
10:00 am
Meeting Materials Here

May 2, 2026
10:00 am
Fosco Park Community Center
1312 S Racine Ave, Chicago, IL 60608